Industry News

Cable laying methods

1. What Are The Requirements For The Installation Distance Of The Bracket In The Cable Trench?

Answer:

  1. When the cable’s outside diameter is equal to or less than 50mm, support  should be added every 1m
  2. When the outside diameter is greater than 50mm, cable support should be put in place every 0.6m.
  3. For a single cable in a triangle, every 1m should be tied firmly, and for a vertical device, every 1 ~ 1.5m has to have fixed support.
 

2. How To Deal With The Installation Of Power Cables And Control Cables In The Same Bracket?

Answer: Power cables and control cables should generally not be laid in the same bracket. However, in a scenario where the control wire and cable and power cable are laid in the same frame, a separation plate should be applied.